Drones lift solar panels at Bentley
More than 2,000 solar panels weighing 55 tonnes have been lifted onto the roof of Bentley Motors' paint shop facility in Crewe using heavy-lift cargo drones. AutoSpray Systems carried out the flights for main contractor Push Power, with roof loading limits meaning the drones carried two panels per flight rather than landing full pallets on the roof of the live site in Cheshire.

Nov 23, 2026
More than 2,000 solar panels weighing a combined 55 tonnes have been lifted onto the roof of Bentley Motors' paint shop facility in Crewe, Cheshire, using heavy-lift cargo drones. The flights were carried out by drone operator AutoSpray Systems, with Push Power acting as main contractor for the solar installation, as reported by Construction Enquirer on 23 November 2026.
The panels were delivered to site on pallets of 36, each pallet weighing close to one tonne. Structural loading limits on the roof meant that full pallets could not be landed, so the drones transferred two panels per flight, with each panel weighing 27.3kg. The work was carried out on a live site.
Rooftop solar installations on large industrial buildings usually rely on cranes or other lifting equipment to raise materials to roof level, which requires ground space and lifting plans and must be coordinated with activity on occupied sites. The Crewe project shows cargo drones being used for this task at a commercial scale, with loads broken down to suit the capacity of the roof rather than the lifting equipment.
Andrew Sproson, co-founder and chief operating officer of AutoSpray Systems, said: "This project represents a major milestone for commercial drone operations in the UK." Andy Khan, managing director of Push Power, said the cargo drone technique offered a faster, safer, cleaner and more efficient way to position rooftop photovoltaic (PV) panels, and that the company was pleased with the results.
Bentley's Crewe site is the carmaker's headquarters and manufacturing base. The companies involved have not published details of the installed generating capacity, the number of flights required, the time taken to complete the lifting operation or the aviation approvals obtained for the flights, so it is not yet possible to compare the cost and programme of the drone method directly with conventional lifting.
Related Posts
Kane secures £40m Victoria Street package
Building services specialist Kane Group has secured a £40m contract for the mechanical, electrical and plumbing package on the refurbishment of 171 Victoria Street, the former John Lewis head office in Westminster, where Sisk is main contractor. The works will be delivered on a design and build basis while retail units stay open, with prefabricated elements made off-site.
Housebuilders face scrutiny over renewable claims
New SBTi reporting rules will require large energy users to disclose how closely their electricity use matches renewable generation hour by hour. Good Energy says 40 UK real estate and homebuilding businesses are likely to fall into the highest category, and that tariffs marketed as 100% renewable may look very different under the new approach.
Aira reports heat pump bill savings
Aira has published a full year of performance data from its UK heat pump fleet, reporting average annual bill savings of £370 for customers who switched from a gas boiler and an average seasonal performance factor of 3.98. The figures, covering November 2025 to October 2026, follow an Autumn Budget that backed heat pumps but reduced Warm Homes Plan funding.