Major accessibility upgrades coming to Tenby Station providing step-free access to both platforms for the first time

Passengers using the popular West Wales station are set to enjoy easier, more accessible journeys thanks to Network Rail’s upcoming upgrades. Supported by the Department for Transport’s Access for All programme, and the Welsh Government, the project will see the construction of a brand-new fully accessible footbridge complete with lifts. Once complete, the upgrades will […]
Tenby AfA digital mock up_cropped

Nov 14, 2025

Passengers using the popular West Wales station are set to enjoy easier, more accessible journeys thanks to Network Rail’s upcoming upgrades.

Supported by the Department for Transport’s Access for All programme, and the Welsh Government, the project will see the construction of a brand-new fully accessible footbridge complete with lifts.

Once complete, the upgrades will make a real difference for disabled people, parents with pushchairs, and those carrying luggage in the busy town – helping to make rail travel more inclusive and convenient. The investment also supports wider goals to encourage public transport use and reduce carbon emissions across the region.

Network Rail’s contractor, AmcoGiffen, will begin setting up the site compound in December 2025. This will include fencing off an area of the station car park near the air cadet huts, resulting in a temporary reduction in parking spaces.

“We’re delighted to be improving accessibility at Tenby Station, ensuring that all passengers can travel with confidence and independence,” said Helen Hodgson, Senior Sponsor, Network Rail Wales and Borders route.

“These upgrades will make a real difference for everyone using the station and reflects our commitment to building a more inclusive and sustainable railway for the communities we serve.”

Most work will take place during the day, though some overnight activity will be required while the railway is closed, for safety reasons. The station will remain open to passengers while work takes place. Planned working hours are as follows:

Daytime: 7:30am to 6:00pm

Overnight: 10:00pm to 6:00am

Work will continue throughout 2026, with the new facilities expected to open by Christmas 2026.

Community engagement event

Network Rail will host a public drop-in event for anyone wishing to learn more about the plans on Wednesday 19 November, between 3:00pm and 7:00pm, at St Mary’s Church, High Street, Tenby (SA70 8AP). Members of the project and contractor teams will be available to answer questions and discuss the planned improvements.

Network Rail is committed to keeping disruption to a minimum and will provide regular updates to the community through a bi-monthly newsletter. Anyone wishing to receive updates can email CRWales@networkrail.co.uk, referencing AFA Tenby in the subject line.

Related Posts

Sixty Years Safeguarding Britain’s Shores
Sixty Years Safeguarding Britain’s Shores

For more than six decades, the National Trust has been at the forefront of efforts to protect Britain’s coastline. What began in 1965 as the Neptune Coastline Campaign has grown into one of the most successful environmental fundraising initiatives in the world,...

Wates and PWR Tackle Gender Misconceptions
Wates and PWR Tackle Gender Misconceptions

At Tower Bridge House on 21 October 2025, industry and sport came together in an inspiring show of collaboration. Wates Construction and Premiership Women’s Rugby (PWR) hosted a thought-provoking roundtable titled Breaking Boundaries – Tackling Gender Misconceptions...

#