Line speed improvements at Cannock

As part of the extensive programme of enhancements and renewals work to the London North Western and East Midlands route, VolkerRail; over the course of three consecutive weekends, has delivered track work for Network Rail to facilitate line speed improvements through the Bloxwich area. Video footage shows the team undertaking renewals and realignment works at […]

VolkerStevin Logo

Feb 15, 2018

As part of the extensive programme of enhancements and renewals work to the London North Western and East Midlands route, VolkerRail; over the course of three consecutive weekends, has delivered track work for Network Rail to facilitate line speed improvements through the Bloxwich area.

Video footage shows the team undertaking renewals and realignment works at Bloxwich level crossing, as well as the abolishment of a the existing level crossing.

The team laid over 4,200t of ballast and 2,000 sleepers throughout the 156 hours of possession time that will eventually increase line speed to 60mph from 45mph.

Graham Shaw, VolkerRail senior project manager said: “Cannock has been a challenging project from its inception, however, the team in collaboration with Network Rail and other major stakeholders are working extremely hard to ensure the ORR milestone of May 2018 is met.”

Related Posts

White hard workman's hat, with measurement ruler on top of a piece of paper with measurements and sketches on a plastered floor
Perega appointed on major Horsham residential development 

Engineering-led approach to deliver 183 houses and five apartment blocks within Taylor Wimpey’s Crawley masterplan. LONDON, UK - May 5th 2026 - Perega is tackling some of the South East’s toughest water neutrality requirements and fifteen metres of unstable made...