Laing O’Rourke wins Khazna Data Centre project
in the heart of Dubai Design District
Laing O’Rourke Middle East has been appointed by Khazna Data Centres (Khazna) to design and build a 21.45MW data centre facility and office space at Dubai Design District. It is the fifth data centre under a main contract that the company will deliver for Khazna in the Middle East. The data centre building, to be […]

Nov 17, 2022
Laing O’Rourke Middle East has been appointed by Khazna Data Centres (Khazna) to design and build a 21.45MW data centre facility and office space at Dubai Design District. It is the fifth data centre under a main contract that the company will deliver for Khazna in the Middle East.
The data centre building, to be constructed within the 26,000 m2 plot, contains four separate pods each with two data halls totalling 5MW per pod, plus seven auxiliary data halls totalling 1.45MW. Laing O’Rourke’s scope includes the design, engineering, procurement, construction, and commissioning of the data centre building plus the technical fit out for each of the four pods and auxiliary data halls.
In addition, the scope of works includes a three-storey office building with an enhanced façade. The project will be constructed and certified in accordance with Uptime Tier III Design which means it can be maintained without the requirement for a total shutdown or equipment replacement. The centre will also meet the sustainability criteria of Leadership in Energy and Environmental Design (LEED) Gold and target a power usage effectiveness (PUE) of below 1.5, making it highly efficient for the region.
Jason Lowe, General Manager for Laing O’Rourke’s Middle East business, said: “We are delighted to extend our long-term client relationship with Khazna on this prestigious data centre project. Integrating our Group’s capability for design management, construction, MEP and fit-out talents in one team provides clients with a clear advantage in terms of surety of delivery.”
Kevin Ayling, Senior Director – Technical Programme Management, Khazna Data Centres, commented: “We are pleased to continue our relationship with Laing O’Rourke with this project. The team submitted the best overall bid in terms of HSE and performance management as well as demonstrating proven data centre construction quality and capability.”
The first phase of the project will be handed over to Khazna in September 2023, allowing for tenant deployment, with the full project completing in quarter one of 2024.
Khazna Data Centres is growing its network of hyperscale data centres across the UAE and has plans to expand its network globally.
Related Posts
Shawbrook strengthens South East Development Finance team with two appointments
Shawbrook grows South East Development Finance team with two appointments Joseph Wilson and Aaron Cummings join to support developers and brokers across the region Appointments follow Shawbrook surpassing £3 billion in development funding and 10 years in the market...
ISUZU UK Gives An ‘Electrifying’ Round Of Applause For ‘Masters Of The Universe’, Released In UK Cinemas On 3rd June
MASTERS OF THE UNIVERSE is a new live-action feature film from Amazon MGM Studios and Mattel Studios, based on the iconic franchise Isuzu UK in-dealership and social media collaboration with MASTERS OF THE UNIVERSE highlights the power and performance of the new Isuzu...
Firecrest Construction Completes 40 Bed Care Home For Exemplar Health Care
Firecrest Construction has successfully completed the complex delivery of a new 40 bed care home in Bury town centre for Exemplar Health Care. As principal contractor to the scheme, Firecrest delivered the job on budget and on time, handing over after 64 weeks...